Contractor finds unsuitable material on Frangiro Road; schedule and scope adjusted

Town of Cutler Bay Town Council · December 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Kimley‑Horn reported the Frangiro Road project encountered localized unsuitable materials below grade that must be removed and replaced with clean fill, pushing parts of Work Zone 1 toward February 2025 and extending Work Zone 2 completion into March 2025; staff said they are coordinating dust control and community outreach.

Town engineering consultants updated the council on construction progress on Frangiro (Rancho) Road, reporting that drainage installation is complete in Work Zone 1 and ongoing in Work Zone 2 but crews encountered localized pockets of unsuitable materials several feet below grade that cannot be compacted and must be removed and replaced with clean fill.

Gary Rotay of Kimley‑Horn said the unsuitable materials prevent reuse…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans