Methacton SD design team lays out four renovation options for High School; board sets review schedule and presses for more time and public input
Summary
Design consultants presented four feasibility options for Methacton High School that all include baseline repairs and upgrades; the board planned visual presentations Aug. 19 and Sept. 16 and tentatively set an Oct. 28 vote while members pressed for earlier review, more detailed cost breakdowns and stronger public outreach.
Get email alerts on the High School Renovation topic
No spam. Unsubscribe anytime.
Design consultants from the Schroeder Group presented four feasibility options for renovating Methacton High School at the July 22 Methacton School District Board meeting, and board members pressed the team for clearer cost breakdowns, phasing information and more public engagement before a planned vote.
Josh and Devin Bradbury of the Schroeder Group outlined a framework that the consultants said will be evaluated for cost, constructability, phasing and educational impact. The consultants said each option includes a baseline package of work — building-envelope repairs (roof, windows, masonry), full mechanical/electrical/plumbing upgrades, and safety, security and ADA improvements — intended to make the building "warm, dry and safe." Visual concepts are scheduled to be shown at an Aug. 19 work session, with a property-committee update Sept. 9, final concept presentation Sept. 16 and an anticipated board vote Oct. 28.
The team described two renovation-dominant options (1a and 1b) and two more extensive options that include new construction (2a and 2b). Option 1a, described as the lowest-cost path, would cover priority-1 work and add a new pool, a fitness/wellness center and a life-skills apartment while bringing one priority-2 element (a Fab Lab) into the vacated pool footprint. Option 1b would add a renovated commons for a "lunch-and-learn" program, reconfigure smaller classrooms on the second-floor west wing to standard sizes and renovate performing-arts spaces. Option 2a would include new construction such as a new auditorium and partial removal of the west wing to improve internal circulation; 2b offers alternative layouts for similar circulation improvements.
Board members repeatedly urged the design team to provide more detailed cost breakdowns for specific scopes — for example, isolating the cost to standardize classroom sizes so the board can consider reprioritization. "Are we going to be able to identify that separately?" asked Mister Winters, requesting scope-by-scope figures. The consultants said preliminary cost ideas may appear in August, with firmer estimates by September and ongoing refinements through October.
Several directors said the current schedule feels compressed. Speaker 9 requested a special meeting in early September or an earlier preview of the final concepts so directors would have time to digest materials before the Sept. 16 work session and the October vote. "If we present it to us for the first time, say, September 10 or September 11, you present it to us for the first time, I think it's fine...but then we have a week to process," Speaker 9 said. The design team agreed to consider the request and to provide a more definitive timeline with deliverables; staff also raised the possibility of pushing the vote into November if necessary to allow adequate review.
The consultants said a separate meeting focused on the natatorium will review how a new pool has been incorporated into phasing and what early-bid packaging might look like; they also said site-level options for circulation and parking will be coordinated with the township. Devin noted a township meeting is scheduled next week to identify potential permitting or sequencing hurdles.
Public commenters urged broader public outreach and clearer materials. John Andrews asked for readable, economical public materials rather than slide printouts with white-on-black formatting, and one commenter called for public sessions and documentation to enable genuine public feedback before substantial spending decisions.
What’s next: the design team will provide a refined timeline and deliverables, visual concepts will be shown at the Aug. 19 work session and the board will consider scheduling a special meeting in early September to allow additional discussion before the Sept. 16 work session and the planned Oct. 28 vote.