Summary

The commission approved minutes, a broad consent calendar (contract amendments and a Muwekma Ohlone agreement), the March 2016 WSIP revision (budget and schedule), Clean Power SF net energy metering and a set of contract amendments and appropriations. Several items passed unanimously; staff were directed to file state notices and return with financing and schedule analyses where requested.

The San Francisco Public Utilities Commission took multiple formal actions at its April 26, 2016 meeting. Key outcomes are summarized below:

- Minutes approved: Commissioners approved the minutes of the March 22 meeting (motion carried).

- Consent calendar approved (Item 9; passed unanimously): The consent calendar included amendments and authorizations for agreements CS200, CS244B (increase $4,500,000 and extend 3 years), CS225R, CS303 (increase $50,000 and 4‑month extension), CS361 (increase $75,000 and 8‑month extension), CS963 (extend up to 2 years and 7 months), award of contract HH982 ($9,171,000 to Robert E. Boyer Construction), contract adjustments for WD‑2696 and WD‑2503R, WW589 final payment and a 36‑month agreement with the Muwekma Ohlone Tribe (not to exceed $208,000).

- WSIP revision approved (Item 10): The commission endorsed the March 2016 revised WSIP, which adds four WSIP closeout projects, extends the program to December 2019 and sets a revised program budget of approximately $4,845,500,000 (a net $80,000,000 increase). Staff will send the required notice of change to the state under the California Water Code.

- Clean Power SF NEM and time‑of‑use rates (Item 14) adopted as amended: Commissioners amended the resolution to remove a broad ongoing delegation of rate authority to the General Manager and to add missing footnotes to attachments; the amended item passed. Staff will publish public materials comparing Clean Power SF NEM compensation to PG&E and proceed with program launch steps.

- Contract and appropriation actions (Items 16–21): The commission approved additional contract amendments and authorizations including: Amendment #3 to CS913 (time extension), Amendment #1 to CS1010 (increase $80,000, one‑year extension), a memorandum of agreement with Tuolumne County (not to exceed $2,365,354 for six years) and a supplemental appropriation request of $5,937,594 for the Warrnerville substation upgrade.

- Closed session: The commission convened closed session on litigation matters. Upon return, the commission announced a settlement of item 26; item 27 came off calendar. Commissioners voted not to disclose closed session discussion.

These votes either authorize staff to begin the specified next steps or to file statutorily required notices; several items included direction to return with further financial or schedule detail.