Votes at a glance: SFPUC approves multiple contract actions, financing authorization and policy steps
Summary
At its March meeting the SFPUC approved the minutes, consent calendar contract awards, several contract amendments and contingency increases, authorized the General Manager to negotiate/terminate an emergency Lower Cherry Aqueduct contract, expanded authorization to pursue State Revolving Fund loans, and approved groundwater and job-training resolutions.
Get email alerts on the Meeting Votes topic
No spam. Unsubscribe anytime.
The San Francisco Public Utilities Commission took a series of formal actions at its March meeting. Key motions and outcomes (voice votes, motions carried unless noted):
- Approved minutes of 02/24/2015 (motion moved and seconded; carried).
- Consent calendar: Approved multiple contract actions, including: approval of plans and award of contract WD2750 to Engineering Remediation Resources Group, Inc. for $9,210,716; acceptance of contract WW546R (total $4,046,362); various final payments and contract modifications listed on the consent calendar (motion carried).
- Item 9: Approved amendment number 5 to agreement CS 8 20 with URS Corporation, increasing the agreement by $1,000,000 (subject to Board of Supervisors approval under Charter Section 9.118).
- Item 10: Approved amendment number 4 to agreement CS893 to extend the agreement duration by one year with no change in the agreement amount.
- Item 11: Authorized the General Manager to continue negotiations with Flatiron West on the Lower Cherry Aqueduct emergency rehabilitation contract and, if negotiations fail, to terminate or close out the contract and pursue a low-bid construction approach. Staff reported ~$3,000,000 expended to date from an original $14,000,000 contract.
- Item 12: Authorized an increase in the construction contract duration contingency for contract WD2629 (seismic/work related to Beta Vision pipeline); motion carried.
- Item 13: Approved an increased cost contingency of $522,328 and an increase in contract duration for WD2641R to address drought-related delays and extended wetland establishment; motion carried.
- Item 14: Authorized staff to expand previous authorizations to include State Revolving Fund (SRF) loans in addition to wastewater revenue bonds for an aggregate principal amount printed in the item as $819,035,941. Staff reported SRF loans would likely reduce borrowing cost (roughly 1.7% base rate, ~2.5% all-in) versus ~4.5% for revenue bonds, translating to an approximate $2 million per $100 million annual debt-service saving (about $0.40/month per customer per $100M financed). The commission voted to move the ordinance to the Board of Supervisors for the loan application process.
- Item 15: Adopted action establishing SFPUC as the Groundwater Sustainability Agency for specified basins within the city and county (public hearing concluded; motion carried).
- Item 16: Adopted a resolution of intent to prepare a Groundwater Sustainability Plan for the North West Side basin; staff will prepare draft plan for public review and return to commission.
- Item 17: Adopted a resolution supporting the development of a Job Training Academy at Gleneagles Golf Course (motion carried).
- Closed session (Item 20): The commission announced a settlement in existing litigation (Arturo Torres et al v. City and County of San Francisco) and voted not to disclose settlement details.
All motions were announced as passed by voice vote during the meeting; the transcript does not provide a full roll-call vote tally by commissioner name for each item.