PUC approves multi-million-dollar contingency transfers for Irvington Tunnel and WD2551
Summary
The commission authorized transfers to construction contingencies for the Irvington Tunnel (WD2581) and contract WD2551 to cover pending change orders and risks, including water seepage and rock conditions; both items passed by voice vote.
The San Francisco Public Utilities Commission approved two contract contingency transfers to cover pending change orders and construction risks.
Irvington Tunnel. Jeet Bajuwa, manager of the Project Management Bureau, explained the request to move $8,005,495 and a 53‑day extension into construction contingency for contract WD2581 (Irvington Tunnel) to fund approved and potential change orders tied mainly to water…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat