SFPUC previews 525 Golden Gate headquarters: wind turbine, water harvesting and LEED Platinum goal

San Francisco Public Utilities Commission · January 12, 2010
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project director Shelby Campbell told the commission the new SFPUC headquarters at 525 Golden Gate will pursue LEED Platinum, include a wind turbine, rainwater/graywater harvesting (≥3,000-gallon storage), childcare, and a local-hire emphasis; construction expected to start in May with completion targeted in 2012.

Shelby Campbell, project director for the SFPUC’s new headquarters at 525 Golden Gate, presented design development and a construction schedule on Jan. 12, 2010. Campbell described sustainable design features that will be pursued to achieve LEED Platinum and to demonstrate innovations in energy and water use.

Key features: Campbell described a public lobby with a visible wind turbine, a two‑level childcare center and a grand interior stair. The building plan includes on-site stormwater and graywater treatment, and a basement storage tank of at least 3,000 gallons to supply nonpotable uses when rainwater is insufficient. "We're going beyond maximum credits available for water efficiency... We will have a treatment for both stormwater and gray water and a 3,000 gallon or greater storage tank in the basement," Campbell said.

Energy and sustainability goals: the design team is targeting a combination of solar and on-site renewables; Campbell said the building could generate a share of its power with on-site renewables and that the design team is pursuing every available LEED innovation credit as a teaching tool.

Schedule and procurement: demolition and micropile work are under way; micro-pile installation is scheduled through March, crane installation in April and above-grade work to start in May. Contractors report packaging work with local-hire targets; the project team said early trade packages for demolition, micropiles and curtain wall came in under budget.

Next steps: staff will continue design development, validate costs with detailed estimates and return with construction documents and outreach for May bid packages. The PUC expects to use the building as a demonstration project for urban sustainability and to publicize building performance via a lobby dashboard for energy and water metrics.