PUC outlines new quarterly reporting for WESIP change orders as some projects near 10% thresholds

San Francisco Public Utilities Commission · September 22, 2009
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

PUC staff presented a quarterly change-order status report for the Water Enterprise System Improvement Program, explained categories of change orders and thresholds that trigger commission approval, and highlighted projects nearing the 10% change-order threshold.

PUC staff on Sept. 22 rolled out a quarterly change-order dashboard and described new quality-management steps intended to reduce design errors that drive change orders in the Water Enterprise System Improvement Program (WESIP).

What was presented: Harlan Kelly, Assistant General Manager, explained the spreadsheet columns — original contract, approved change orders, pending changes, revised contract total and percent complete — and defined three categories for changes: (1) unforeseen conditions discovered in the field, (2) owner-directed changes, and (3) errors or omissions in design. Kelly said the PUC plans to report this information quarterly and to provide advance notice when projects approach the 10% change-order threshold that requires commission approval.

Examples and numbers: The Standby Power project was reported at roughly 90% complete with about 9.7% in approved change orders (driven in part by new Bay Area Air Quality Management Board criteria and sole-source equipment additions). The Harry Tracy Water Treatment short-term improvements were about 70% complete with approximately 5.5% approved changes and roughly 9.6% of additional pending changes being evaluated; staff said some pending items are uncertainty-driven and may not be approved in full.

Risk-control steps: Staff described third-party constructability and bidability reviews, operation liaison positions that incorporate field feedback into design, and the use of a construction-management information system for near-real-time tracking. Contract-level contingency of about 10% was noted as standard industry practice, but commissioners and public commenters asked for project-specific contingency burn-rate fields to be added.

Follow-up: Staff agreed to consider adding a remaining-contingency indicator per project and to share the quarterly change-order report going forward; commissioners said the document provides needed transparency but cautioned against administrative delay that would hold up construction progress.