DPH bond update: projects advance but a multi‑million-dollar deficit remains; agency seeks alternatives

San Francisco Health Commission · September 5, 2023
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DPH and Public Works reported progress on ZSFG projects funded by the 2016 health and safety bond but said supply-chain and pandemic-related pricing left an estimated $83–111 million funding gap; staff outlined cost-reduction and alternative-funding strategies.

Capital projects staff updated the Health Commission Sept. 5 on the Public Health and Safety bond program and related hospital projects.

Mark Primo (Capital Projects Oversight) and Terry Salts (Zuckerberg General facilities director) described efforts to close a roughly $111 million projected deficit on 2016 bond projects. After accounting for identified alternate funds and abatements the shortfall could fall to about $83 million, they said. Strategies include pursuing state grants (including funds for adolescent behavioral health), applying interest earnings from bond proceeds, leveraging a recent MOU with the San Francisco General Foundation (MOU cited at $18 million), pursuing a potential 2024 bond with a $33 million critical infrastructure category, reducing perceived contractor risk and scope where feasible, and sequencing early demolition to lower bid premiums.

Public Works project manager Joe Chin provided project-level updates at Zuckerberg San Francisco General (Building 5): the Dallas project and seismic upgrades are in active construction, public health lab demolition and trenching are underway, and the psychiatric emergency services (PES) early-demolition project is 99% complete with main renovation approvals pending. Several projects target completion in late 2024 or early 2025; the adolescent behavioral health inpatient/outpatient scope is included in the grant and has a projected completion date in 2027.

Commissioners asked clarifying questions about adolescent behavioral health infrastructure and project timing; staff said they are still establishing grants and planning and that construction will follow grant and procurement steps. No formal vote was taken; staff will return with more detailed budget mitigations as contracts and funding strategies mature.