PUC approves invitation to bid for GPA’s typhoon‑proof transmission & distribution facility

Guam Public Utilities Commission · March 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved GPA’s invitation to bid for a two‑story, typhoon‑resistant transmission and distribution administration and disaster‑recovery facility at the Terido site, with an estimated cost previously reported between $14.8 million and $17.2 million and FY25 CIP funding already budgeted.

The Public Utilities Commission voted unanimously to authorize the Guam Power Authority to proceed with an invitation to bid for a new, two‑story, typhoon‑proof transmission and distribution (T&D) administration building and disaster‑recovery office at the Terido property.

PUC legal counsel (speaker 11) said Rim Architects prepared design work and earlier cost estimates placed construction near $14.8 million; GPA updated estimates used current market data and cited an approximate cost of $17.2 million in recent filings. The new facility will replace aging steel and tin structures at the existing site, provide a disaster‑recovery office for power‑system control and IT systems, and include demolition, new parking, utilities, interior finishes and fire suppression.

The DPA urged approval, citing safety concerns during storms and the need for a stable, centralized operations location. Commissioners noted the project is already budgeted in GPA’s CIP (with about $5 million recorded for FY25), discussed co‑location and redundancy with other control centers, and agreed that the current T&D buildings are unsafe in severe weather.

The commission moved, seconded and voted ‘aye’ on the invitation to bid; the motion passed unanimously.

Next steps: GPA will issue the invitation to bid consistent with the approved procurement documents and return to the commission as required for contract awards exceeding review thresholds.