Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Fire Commission reviews near'completion Station 49 and progress on floating Station 35
Summary
Assistant Deputy Chief Dawn DeWitt told commissioners Station 49 is in final punch-list work with a projected completion date of April 26 and an early June move'in; Station 35 remains on track for summer 2021 but is awaiting electrical and water hookups and regulatory permits.
Assistant Deputy Chief Dawn DeWitt told the Fire Commission on March 24 that Station 49 (the ambulance deployment facility funded through the 2016 health and safety bond) is in the final punch-list stage and expected to reach final completion on April 26, with an anticipated move'in in early June 2021.
"Final completion date is now April 26," DeWitt said, noting the project stayed on budget despite COVID'related supply chain delays and subcontractor shortages. She described…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
