SFMTA: first issuance of 2014 transportation bond under way; second issuance planned
Summary
SFMTA reported $66 million issued of the $500 million 2014 Transportation and Road Improvement Bond, with $22 million expended and planning underway for a second issuance of roughly $184 million to fund projects across eight categories.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Monique Webster, senior manager of capital finance at the San Francisco Municipal Transportation Agency, told the committee the 2014 Transportation and Road Improvement Bond authorizes $500,000,000 across eight project categories. She said SFMTA has issued $66,000,000 to date; from that issuance the agency reported $22,000,000 in expenditures as of June 30 and about $17,000,000 encumbered for a combined roughly 60% of the first issuance.
Sean Kennedy (SFMTA) reviewed recent project milestones: a transit boarding island completed at Eleventh and Harrison, curb work done at Mission and Turnbull, and several corridor projects under construction (Chestnut, 5 Fulton, Judah between Arguello and Ninth). Kennedy said Judah work has begun and will be a roughly two‑year construction project; 5 Fulton is projected to be completed by April 2018.
Webster told members the agency received a supplemental appropriation moving $26,200,000 of the first issuance into facilities upgrades to accelerate construction‑ready projects, and that SFMTA is working with the comptroller and mayor’s offices on a second issuance currently estimated at about $184,000,000 to cover all eight categories and roughly 37 projects.
Committee members pressed SFMTA on change orders, rebids driven by LBE goals (the 5 Fulton project was rebid three times), measurable time savings from projects, and effects on small businesses during construction. SFMTA said project‑level before/after travel‑time measures exist and cited an example of ~1 minute 40 seconds of travel‑time savings from a contraflow lane project; the agency also described business working groups and outreach mechanisms to collect and respond to feedback.