OCII to contract SF Public Works for Transbay Park design under $3.9M MOU
Summary
The commission authorized a memorandum of understanding with San Francisco Public Works for design and project management services for Transbay Park not to exceed $3,895,613 through Sept. 18, 2021; staff said Public Works will lead schematic design, public outreach and construction management, with OCII SBE rules applied to subcontracts.
Get email alerts on the Transbay Park topic
No spam. Unsubscribe anytime.
The commission approved an MOU on Sept. 18 to hire San Francisco Public Works to design and manage construction of Transbay Park for an amount not to exceed $3,895,613 through Sept. 18, 2021.
Presenter Cisse described Transbay Park as slightly over one acre and positioned between Block 4 and Block 2 of the temporary terminal site. Cisse said Public Works’ landscape architecture team will act as the lead designer; once OCII transfers the completed park to the city, it is efficient for Public Works to develop the schematic design and manage construction bidding and procurement.
The MOU covers concept design through construction bidding; staff noted the budget includes a base services fee and allowances for as‑needed services (roughly $1.2 million for those allowances). Cisse said the schedule calls for public outreach and concept design in fall/winter, schematic design return to the commission in about a year, bidding of construction documents mid‑2020 and construction completion targeted for 2022.
Commissioners confirmed that OCII’s SBE policies and local‑hire goals apply to any subcontracts under the MOU and welcomed interagency cooperation. The motion to approve the MOU carried on a roll‑call vote of four ayes, one absent.
Staff said they will return with schematic designs for commission approval and will ensure subconsultant opportunities comply with OCII SBE requirements.