Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Commission probes soft‑story retrofit progress and enforcement as Sept. 15 deadline nears

Building Inspection Commission · June 21, 2017
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DBI managers reported progress on the soft‑story retrofit program (about 4,900 buildings in ordinance: 2,800 permits issued, 1,300 certificates of completion), while engineers and commissioners raised concerns about construction quality, contractor capacity and whether DBI has sufficient enforcement and outreach to meet Tier‑3 deadlines.

DBI staff told the commission the soft‑story retrofit program has made substantial progress but faces capacity and quality-control challenges as upcoming deadlines loom.

"We started in 02/2013...4,900 buildings are in the ordinance. We've issued 2,800 permits and 1,300 certifications of completion," program manager Robert Chun said, outlining plan‑check and quality‑control procedures including 5% senior spot checks, staff training and reliance on third‑party special inspectors.

Deputy Director Ed…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans