Planning commission approves Crocker Galleria renovation with conditions after split vote
Summary
The commission approved interior and exterior improvements to Crocker Galleria at 50 Post Street to increase rooftop public access and improve street engagement. A continuance motion failed and the alternate approval passed 4–2 with direction for additional design coordination and enhanced POPOS signage.
Get email alerts on the Crocker Galleria 50post topic
No spam. Unsubscribe anytime.
The Planning Commission approved a downtown project authorization Dec. 5 to modify the Crocker Galleria at 50 Post Street and improve public access to rooftop open space, upgrade wayfinding, and reconfigure ground‑floor access. Staff described the project as largely interior alterations with limited exterior changes and recommended approval with conditions including final signage and wayfinding work.
Project representatives said they had worked with tenants and had received a letter of support from the Galleria Merchants Association. The sponsor’s architect described plans to ramp up ADA access, enlarge public entrances, and replace the Sutter Street storefront step condition with a more accessible slope and operable doors.
Commissioner Moore asked for Historic Preservation Commission review; a continuance motion to seek further advisory review failed on a 3–3 tie. An alternate motion to approve with conditions passed 4–2 (Commissioners Moore and Richards opposed). The commission required the sponsor to continue working with staff on design refinements and to incorporate robust POPOS signage and exterior lighting improvements.