Owner representative asks Board to delay penalties for 1686 Market smoke‑and‑odor NOV due to permit delays

San Francisco Board of Appeals · May 19, 2021
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

An attorney for the owner of 1686 Market Street told the board that required permits (fire alarm, hood suppression) and sound‑barrier components for a pollution control unit are delayed by permitting processes and supply chain issues; he asked that penalties tied to certificates of final completion be deferred.

During general public comment Justin Zucker of Rubin, Junius & Rose updated the board on an NOV appeal for emissions tied to Espritus Steakhouse at 1686 Market Street. Zucker said the property owner agreed to install a new pollution‑control unit and submitted the permit application, but that plan check revealed additional required scopes — a new fire alarm and hood suppression — and that a noise‑mitigating sound wall ordered for the roof is delayed by pandemic‑related supply chain issues. He requested that penalties imposed in the earlier appeal not begin to accrue until three weeks after issuance of the still‑pending fire alarm permit to allow inspection and issuance of the certificate of final completion.