Board continues appeal over AT&T cabinet placement at Cesar Chavez to allow technical evidence
Summary
Neighbors and AT&T disputed placement of a new AT&T surface-mounted cabinet at 3688 Cesar Chavez Street; the Board continued the appeal to allow AT&T and DPW to submit technical exhibits proving alternative sites are infeasible and set a briefing schedule for June 25.
Get email alerts on the Wireless Facility Placement topic
No spam. Unsubscribe anytime.
The Board of Appeals continued an appeal about a proposed AT&T surface-mounted facility at 3688 Cesar Chavez Street to allow the permit holder and the Department of Public Works to submit detailed technical exhibits showing why community‑suggested alternative locations are infeasible.
Appellant representatives argued that AT&T’s proposed cabinet would eliminate a legal parking space near a pharmacy, impede disability access and that alternatives discussed on the box walk were not evaluated properly during the hearing officer’s review. The appellant presented photographs, a petition and a letter reporting access issues for customers with disabilities.
AT&T counsel and DPW staff said field engineers conducted site surveys and reported that the suggested alternative locations violated the department’s Surface Mounted Facility (SMF) placement guidelines — including required clearances from driveways, hydrants and other above-ground structures — and that some alternatives would not be ADA-compliant or would require cutting protected trees or obtaining city easements.
Several commissioners said the diagrams and engineering conclusions provided orally were not sufficient; they asked for accurate, scaled drawings and engineering documents that identify clearance dimensions, driveway cuts and other constraints. The Board ordered the permit holder and DPW to submit exhibits documenting technical infeasibility; the hearing was continued to June 25 with a briefing schedule and an opportunity for rebuttal filings.
Next steps: AT&T and DPW to provide accurate drawings and engineering exhibits showing why alternatives are infeasible; materials due per the Board’s June 25 schedule.