Planning commission continues contentious 222 Second Street hearing to Aug. 12 after tie and substitute motions
Summary
Neighbors asked for a one‑week continuance to accommodate residents with pre‑paid travel; project sponsor argued for the Aug. 5 date because architects were unavailable. After debate, a substitute motion to continue items to Aug. 12 carried unanimously.
Get email alerts on the 222 Second Street topic
No spam. Unsubscribe anytime.
The Planning Commission on July 22 considered a public request to continue proceedings on the 222 Second Street EIR and companion cases. Sue Hester, attorney for the 246 Second Street Homeowners Association, told the commission that residents who intended to testify had booked non‑refundable travel and would be unable to attend the earlier date. She asked for a one‑week continuance to avoid unfairly preventing neighborhood participation.
Andrew Junius, representing Richmond’s Fire Properties and the project sponsor, argued the CEQA materials had been available and that the sponsor’s team — notably key architects — were unavailable for the earlier hearing. Commissioners weighed neighbor participation against the sponsor’s scheduling constraints. After an initial tie on a motion, Commissioner Gordon offered a substitute motion to continue items to Aug. 12; the motion was seconded and passed unanimously on roll call.
The continuance preserves additional time for both public review and sponsor presentation; staff confirmed the items will be calendared for Aug. 12. There was no final action on the EIR or companion merits at the July 22 meeting.