Votes at a glance: San Francisco Planning Commission, May 27, 2010
Summary
A summary of actions: the commission continued several items, approved the 45 Lansing extension and the 888 Brandon office allocation (with conditions), approved small‑scale projects (449–451 Mississippi; 969–971 Union), and continued the Verizon antenna and 3400 Mission items for full hearings.
Get email alerts on the Meeting Votes topic
No spam. Unsubscribe anytime.
Key votes and outcomes from the Planning Commission meeting on May 27, 2010:
- Items continued per staff calendar: several cases were continued to later dates, including item 14 (Chapter 31 CEQA notice) to June 24, items 18a/18b to July 8, and item 20 (30 Edith Street) to July 22 (motion passed).
- Item 7 (502 Seventh Street conditional use for ambulance service): Approved on consent (unanimous among present commissioners).
- Item 8 (530 Bush Street Verizon Wireless antennas): Initial motion to approve failed (3‑1). Commission voted to continue the item to June 17, 2010 for a full public hearing with staff present.
- 3400 Mission Street (proposed 7‑Eleven, conditional use): Continued to July 1, 2010 with the public hearing left open to allow outreach between sponsor and neighborhood groups.
- Item 15 (45 Lansing Street extension): Approved a 12‑month extension for the project; sponsor noted interim pollinator meadow stewardship.
- Item 16 (850–870 Brannon / 888 Brandon): Approved office allocation (~138,580 sq ft), removed off‑site parking requirements, and added a condition for sponsor to revisit window profiles to be consistent with historic character; staff added a contingency about potential future jobs‑housing linkage fees based on pending legislation.
- Item 17 (449–451 Mississippi): Commission declined to take discretionary review and approved the variance/replacement deck project.
- Item 19 (969–971 Union): Approved merger of two owner‑occupied units into one.
Several public comments also addressed the Hunters Point/Shipyard FEIR and cultural/archaeological concerns related to the shoreline plan; those items remain subject to ongoing review.