Committee approves forwarding $1.5M loan increase for Sunnydale infrastructure phase, requests SFPUC cost‑share report
Summary
The committee recommended a $1.5M loan increase (to ~$26.6M) for Sunnydale Infrastructure Phase 1A3 to cover weather delays, unforeseen conditions, and temporary power costs; BLA asked for a 30‑day report on SFPUC reimbursement and urged clarity on future cost‑sharing.
The Budget and Finance Committee on Nov. 15 forwarded to the full Board a resolution to increase the city loan to Sunnydale Infrastructure Phase 1A3 by about $1.5 million to a total not to exceed approximately $26.6 million, citing construction delays caused by extreme weather in early 2023, unforeseen site conditions, and expenses for a temporary power connection.
Jason Liu (HOPE SF policy…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat