Committee endorses final modification to airport hotel project contract, approves $4.6 million increase
Loading...
Summary
The committee forwarded Modification No. 5 to the PGH Wong contract for the SFO airport hotel program, increasing the contract by $4.6 million and extending its term; the Budget Analyst recommended approval and said this likely will be the final modification.
The Budget and Finance Committee moved Modification No. 5 to a project-management contract with PGH Wong for the on‑airport hotel project at San Francisco International Airport to the full Board with a positive recommendation. Kathy Weidner (San Francisco International Airport) said the modification would increase the contract by $4.6 million and extend the term to June 10, 2019 (as presented in the committee record) to support the