Committee endorses SFPUC grant actions to support Lower Cherry aqueduct rehab and early intake slope studies

San Francisco Board of Supervisors Budget and Finance Committee · February 9, 2017
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee advanced resolutions for two SFPUC proposals: acceptance of up to $3 million for Lower Cherry Aqueduct rehabilitation (DWR funds) and acceptance of a $404,000 FEMA Hazard Mitigation Grant for early‑intake switchyard slope stabilization studies; both items were forwarded to the full Board with positive recommendations.

The Budget & Finance Committee forwarded two SFPUC items to the Board of Supervisors with positive recommendations.

Lower Cherry Aqueduct rehabilitation: Dan (SFPUC) described emergency rehabilitation work after damage related to the Rim Fire and prior emergency repair phases. He said the agency has incurred about $9.29 million to date and projects future costs of about $4.7 million, with a total program budget of roughly $14 million. The committee considered a resolution authorizing the SFPUC general manager to accept and expend up to $3,000,000 in grant funds (from the California Department of Water Resources) to help fund the project. The Budget & Legislative Analyst recommended an amendment to clarify that the resolution should authorize both acceptance and expenditure of the $3,000,000 and to acknowledge the approximately $11 million in matching costs; the committee adopted the amendments and moved the item to the full board with a positive recommendation.

Early Intake switchyard slope stabilization: Separately, SFPUC presented a FEMA Hazard Mitigation Grant Program pre‑award/Phase 1 allocation of about $404,000 to fund engineering, environmental studies and scope definition for slope stabilization measures — including rock‑fall fences, vegetation and drainage — at the early intake switchyard that serves regional Hetch Hetchy facilities. The BLA noted that the $404,000 would replace previously allocated PUC funds and identified a $190,000 match; the committee recommended the item forward and it passed without objection.

Both items will appear on the Feb. 28 Board agenda for final action.