Court approves change orders and special-inspection contract for Road Department redevelopment; staff plan drainage fixes
Summary
Fiscal court approved multiple construction change orders and awarded a special-inspection contract for the Road Department/Lakeview Park redevelopment. Road staff described planned drainage fixes including lowering drains and installing trench drains and concrete aprons to prevent winter ponding.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Frankfort — Franklin County moved forward on the Road Department redevelopment and associated Lakeview Park work, approving a suite of construction change orders and awarding a special-inspection and testing contract to CETCO.
Work and contracting: Project staff presented a series of bid-package change orders to address field conditions and technical clarifications. The court accepted a recommendation to award the special-inspection and testing contract (CETCO) to support quality-control sampling and testing during construction.
Drainage concern and remedy: Several magistrates raised concerns about surface water ponding in the new paved areas. Road Superintendent Duke Wilburn and engineering staff described a plan to lower affected drain inlets by 4 inches and install trench drains with concrete aprons to collect runoff and avoid winter icing: "We're gonna lower the drains by 4 inches and then pour 10 foot concrete," Wilburn said.
Budget and reconciliation: Staff told the court the package of credits and change-order adjustments currently results in a near-budget position, but final reconciliation will be reported at the next meeting; the treasurer said she will present a project-level summary at the next court meeting.
Next steps: The court approved the change orders and the inspection contract during the voting session and directed staff to present a final accounting and any remaining adjustments at the next meeting.