VDOT reports completed resurfacing, Smart Scale projects and gives update on AllPoints broadband permits

Culpeper County Board of Supervisors · December 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

VDOT told the Culpeper Board it completed the 2024 resurfacing program (31.73 centerline miles), finished rural‑rustic segments set for spring surfacing, is advertising the 2025 pavement program (50+ miles), and said AllPoints Broadband has permits but limited on‑the‑ground completion to date.

Mark Nesbitt of VDOT’s Warrenton residency presented the county’s quarterly transportation update, highlighting maintenance and upcoming projects in Culpeper County.

Nesbitt said crews finished the rural‑rustic program for the season on five road segments and that surfacing for those segments is planned in spring. He reported the 2024 pavement resurfacing program is complete — "31.73 centerline miles" — and that about 9.5 miles of that total were surface treatment. The 2025 pavement program is under advertisement with more than 50 miles of plant‑mix scheduled; Nesbitt said he will present awarded projects and paving lists to the board once contracts are finalized.

On Smart Scale and town projects, VDOT noted county and town submissions (Route 3, Route 669/Carricko Mills, a roundabout at Route 3 and McDevitt Drive, and other bike/ped enhancements); some projects are moving into design and advertisement with construction expected in the spring following utility relocations. Nesbitt estimated roundabout construction (Route 3/McDevitt) as roughly an 18‑month project.

VDOT also discussed a bridge superstructure replacement on Hazel River Road (Route 628) scheduled next year pending funding, and confirmed the county’s revenue‑share projects (Reba Road and White Shot Road) are approved but that funds will not be available until about 2028–2029.

On broadband: Nesbitt said VDOT has issued nine permits to AllPoints Broadband (two permits were canceled by the permittee and two additional permit applications were submitted for re‑issuance). He reported construction had commenced on three of the seven existing permits but that no permit segment appeared fully complete to VDOT; he said the county would continue to issue permits to keep crews available while the company addresses resource constraints.

In Q&A supervisors asked VDOT how many miles AllPoints completed; the transcript records an exchange that totaled approximately "2 miles per permit" and a supervisor calculating "6 miles in the last month" based on three permits worked, though VDOT emphasized it had not observed final completions. The board also discussed speed‑feedback signage and coordination with the sheriff’s office for secondary roads and noted a consultant‑led scoping process for a potential Stevensburg Road safety project.

What’s next: VDOT will return with awarded 2025 pavement project details and continue coordination on the Southern Route 29 corridor study and local revenue‑share projects.