City approves $751,524 HA5 street preservation plan to accelerate local paving schedule

City Council of Hondo, Texas · January 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $751,524 HA5 preservation project to advance chip-sealed streets into HA5 sealing; staff proposed using fund balance to cover a $292,524 shortfall so the full work can be completed this year.

Hondo, Texas — The City Council voted Jan. 27 to approve the proposed 2025 HA5 street preservation plan, authorizing $751,524 in work to seal and preserve select city streets.

City manager/staff presented maps and said green and red streets on the plan will be sealed in 2025; the total project cost is $751,524 and staff reported $165,000 already allocated from a tax note originally intended for City Hall upgrades. Staff recommended using $292,524 from fund balance to close the gap so the full list could be completed this year and to keep the city a year ahead on its five-year street plan. "We are going to be about one year ahead in our 5-year street plan," staff said.

Council debated whether to split the project over two years to reduce immediate spending; staff noted the cost of construction is rising and recommended doing the full package now. Council approved the manager’s request; no opposition was recorded.

Next steps: staff will process the procurement and bring any necessary budget amendments back at the quarterly budget cleanup.