Hondo council authorizes KSA task order to prepare runway-closure bid documents

City Council of Hondo, Texas · January 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $29,878 task order for KSA engineers to prepare bid documents for closing Runway 17R-35L and making improvements to Runway 17L-35R at Hondo Municipal Airport; staff said closure will save maintenance costs and is not eligible for federal funding.

Hondo, Texas — The City Council authorized the city manager Jan. 27 to execute a task order with KSA engineers to prepare bid documents for the previously approved closure of Runway 17R-35L and improvements to Runway 17L-35R at the Hondo Municipal Airport.

Airport operations staff described Runway 17R-35L as lightly used — roughly 236 operations out of about 17,000 in 2024, or about 1.5% of operations — and explained that the runway’s pavement friction test showed slow water dispersion (about 20 seconds on the centerline vs. a target of 10 seconds) and surface deterioration. "This runway is not eligible for federal funding," the airport presenter said, adding the city will use a reimbursement mechanism from a bipartisan infrastructure law grant associated with a prior taxiway project to fund the work.

Staff recommended a "skidabrator" friction-recovery method as a lower-cost option that both removes paint contaminants and restores friction; staff estimated engineering fees of $29,008.78 to prepare the bid package and suggested total project costs could be in the low hundreds of thousands depending on options. Council members asked about square footage and long-term effectiveness of skidabrator versus full runway grooving. Staff said runway grooving is more durable but significantly more expensive; the skidabrator would take about 3–4 days of on-site work.

Council approved the task order for KSA to prepare bid documents and to act as the city’s representative in the procurement process; the motion carried by voice vote with no opposition recorded.

Next steps: KSA will solicit bids and provide an engineer's opinion of probable cost to return to council for approval of the construction contract and any required budget adjustments.