City staff reported Topperwine Road Phase 1 is about 90% through redesign but requires additional storm sewer work, small right-of-way acquisitions and coordination with Enterprise Products; updated cost estimate is $6.63M with an additional $2–3M possible for intersection realignment, leaving a funding shortfall against a $2.9M Certificate of Obligation balance.

Converse city staff told the City Council on Dec. 17 that the redesign for Topperwine Road Phase 1 (Meadowgate to FM 1976) is about 90% complete but requires additional stormwater improvements, minor right-of-way acquisitions and coordination with utility owners.

Assistant City Manager Nina Mendez said the updated opinion of probable cost for the project is $6,634,200 and that figure does not include the intersection realignment design or construction management, which staff estimated could add another $2 million to $3 million. “Out of that C of O, we have a balance right now of $2,916,589,”…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans