City staff outlines $83 million in Kingsville infrastructure projects, progress and next steps
Summary
City staff reported roughly $83 million in active projects including GLO wastewater ($7M, ~90% complete), GLO stormwater ($36M, ~55% complete), TxDOT sidewalk/drainage plans (~$9.2M), an animal shelter renovation and a $14M fire-station/equipment package; several projects are nearing bid or signature steps.
City staff told the Kingsville City Commission on May 12 that the city currently has about $83 million in infrastructure work underway and provided progress estimates and next steps for several projects.
Staff said the GLO wastewater project is funded at about $7,000,000 and is roughly 90% complete. The GLO stormwater program, described as 14 separate projects, totals about $36,000,000 and is approximately 55% complete. Staff also described a Texas Water…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat