City staff outlines $83 million in Kingsville infrastructure projects, progress and next steps
Summary
City staff reported roughly $83 million in active projects including GLO wastewater ($7M, ~90% complete), GLO stormwater ($36M, ~55% complete), TxDOT sidewalk/drainage plans (~$9.2M), an animal shelter renovation and a $14M fire-station/equipment package; several projects are nearing bid or signature steps.
Get email alerts on the Capital Infrastructure topic
No spam. Unsubscribe anytime.
City staff told the Kingsville City Commission on May 12 that the city currently has about $83 million in infrastructure work underway and provided progress estimates and next steps for several projects.
Staff said the GLO wastewater project is funded at about $7,000,000 and is roughly 90% complete. The GLO stormwater program, described as 14 separate projects, totals about $36,000,000 and is approximately 55% complete. Staff also described a Texas Water Development Board stormwater package of roughly $10,000,000 that is about 40% complete.
Other capital work detailed by staff included wastewater ultraviolet lights for north and south bands (about $1,000,000, percent complete not specified), an animal shelter building project of about $500,000 that staff said is 90% complete, and a citywide water meter replacement program totaling roughly $6,100,000. Street improvements of approximately $1,400,000 were described as about 65% complete.
Staff told commissioners bids will open in May for a new fire station and equipment package (โ$14,000,000), which the city said will include a new pump truck, a ladder truck and an ambulance. Staff also said the city was notified of an award for a mid-water wastewater project and was awaiting the mayor's signature to finalize the award.
In response to a resident question about Playbrook Street, staff said the contractor will return to remove and redo the work using a mix better suited to South Texas humidity; staff said similar mixes were used in other regions but are being adjusted for local conditions. For the Caesar ditch drainage project, staff announced a groundbreaking on the 29th and that an existing house will be removed to clear the site.
City staff closed by thanking employees and volunteers for service; the mayor and commissioners also recognized volunteers who supported recent community events.