Floresville details CIP timelines: lift station, pool demolition, street designs and event‑center activity
Summary
City staff gave a multi‑item CIP update to council: Highway 97 lift station (mid‑2025), US‑181 lift station design pending easements, River Park pool demolition and phase‑2 works, schematic street designs due Jan. 2025 and downtown infrastructure work planned to support development.
City staff provided the council a monthly update on capital projects and board activity, reporting timelines and next steps for several projects.
Highlights included an estimated Q2–Q3 2025 completion window for a Highway 97 lift station; US‑181 proposed lift‑station site selected with easement work underway…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat