Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Town maintenance flags spring-tank and valve problems; staff proposes engineering review and water-conservation options
Summary
Maintenance staff reported spring-tank overflow and disagreement about a clay valve setting; rural-water and town staff recommended further engineering review, manufacturer consultation and exploring a retention basin to reuse overflow for irrigation if water rights permit.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
During department reports, maintenance staff described recurring problems with a newly installed tank used to store spring water and a "clay valve" suspected of not allowing treated flow to pass properly. A rural-water representative inspected the valve and said the diaphragm setting is adjustable and expressed surprise the valve could not be made to work at available pressures.
Maintenance staff said the town is experiencing overflow from the spring-fed tank and proposed designing the new tank to overflow into a retention basin for irrigation instead of discharging treated water downstream. Staff cautioned that water-rights claims from downstream users could limit reuse options and recommended consulting the state water engineer before redirecting overflow. Staff also discussed rotating engineering vendors periodically and checking who signed off on the original project paperwork.
Council asked staff to follow up with the manufacturer and engineer, to compile signed project paperwork and to explore whether a retention basin is permissible under existing water rights. The maintenance report also noted ongoing work to order spare chlorine-dispensing equipment and to keep a replacement on the shelf to avoid outages.
Next steps: maintenance and rural-water representatives will confirm valve settings with the manufacturer, gather project sign-off documentation, and consult the state water-rights office before pursuing a retention-basin solution.
