Planning Commission approves backyard fiberglass pool at 260 East 75 South
Summary
The Rockville Planning Commission unanimously approved a permit for a fiberglass pool and spa at 260 East 75 South, finding the application consistent with the town's General Plan and building codes. The installer said the pool is ~8,000 gallons, will use an auto-fill, and that any block wall over 5 feet will require separate building plans and footing.
Get email alerts on the Private Development topic
No spam. Unsubscribe anytime.
A majority of the Rockville Planning Commission voted to approve an application to install a residential fiberglass pool and spa at 260 East 75 South after a presentation and technical questions on Dec. 10.
The applicant, representing Premier Pools and Spas, described the project as a prefabricated fiberglass shell to be installed at an existing home owned by Dennis Brooks. The presenter said the pool will be about 8,000 gallons with a roughly 800'gallon spa and that "it's non porous, non corrosive" and will use a UV cleaning system so it "won't use a lot of chemicals." The company also described a 2.7-horsepower variable-speed pump and said the design and plumbing choices produce greater efficiency than older installations.
Commissioners pressed the applicant on construction and code compliance. The presenter said installation requires an engineered cross section and at least a 3-foot concrete coping around the fiberglass shell; the pool will be backfilled with pea gravel and finished with concrete decking or similar surfacing. On barriers, the commission noted an existing Land Use Code requirement: any wall over four feet requires a building permit and footing (Land Use Code section 9.10.18). The applicant said Premier Pools and Spas would not be contracting to build any 5-foot block wall; that work would be separate from the pool permit.
The commission also discussed water sourcing and plumbing safety. Commissioners asked whether the owner would fill the pool from irrigation or culinary (treated) lines and requested notice when the pool is filled so town water managers can anticipate increased demand. The applicant answered that fill will use the homeowner's landscape/irrigation supply with an automatic fill line and that if culinary lines are used a backflow preventer would be required.
A commissioner moved to approve the application, noting it "falls within the Rockville General Plan and the Rockville Land Use Code and the International Residential Building Codes" and including the reminder that a block wall of five feet or more needs separate plans and footing per the code. The motion was seconded and approved in a roll-call vote recorded in the transcript as unanimous.
The applicant said construction cannot begin until final permits are issued; they estimated delivery of the shell and on-site installation in February, with excavation likely in January or early February after permit approval.