Airport manager details CIP changes: FAA AWOS entitlement, $138,030 city share and apron reconstruction design

Hurricane City Airport Advisory Board · November 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff presented a revised capital improvement plan for Hurricane City Airport: a $270,000 FAA entitlement for an AWOS installation with a $138,030 city contribution, design work for apron reconstruction starting in 2025 and an $800,000 allocation from federal infrastructure funding for future apron work; FAA required a revised airport layout plan tied to a proposed runway extension.

Airport staff updated the board on changes to the airport's Capital Improvement Plan (CIP) after a runway‑widening delay and work delays on the AWOS project.

An unidentified staff presenter described an FAA entitlement of $270,000 for the Automated Weather Observing System (AWOS). He said the city would contribute $138,030 toward the AWOS installation. Staff also outlined a multi‑year apron reconstruction program: design in 2025 followed by phased reconstruction beginning in 2026, with some project money carried into later years.

Staff explained an FAA concern tied to a planned power‑line extension down 1100 West. The FAA would not approve pole heights while the airport layout plan showed a proposed 740‑foot runway extension. Staff said property acquisition and rerouting made the runway extension infeasible; after removing the proposed extension from the layout plan the FAA cleared the power poles and asked the city to commission a revised airport layout plan.

The presentation also noted an $800,000 allocation tied to the Bipartisan Infrastructure Law related to apron work. Board members asked about design scope and whether ramp areas could be enlarged during reconstruction; staff said those details will be worked out during design and when costs are refined.

What happens next: Staff will commission a revised airport layout plan, proceed with AWOS procurement and begin design work for apron reconstruction in 2025, then return with funding and scope details during later board meetings.