Work meeting: town considers $150,000–$300,000 fixes for chronic flooding on 100 West
Summary
At a Gunnison work meeting participants reviewed options to reduce recurring flooding on 100 West, from a $33,000 east-side inlet replacement to larger west-side bubble-up culverts and waterways that could push total costs toward $250,000–$300,000; staff were directed to check utilities, talk with a nearby church about cost-sharing and return with funding proposals.
Get email alerts on the Drainage Improvements topic
No spam. Unsubscribe anytime.
Participants at a Gunnison work meeting spent the hour reviewing engineering options to reduce chronic flooding along 100 West and weighing how to pay for the work.
Speaker 2 opened the discussion by identifying the problem and the general scope: "We're gonna talk about drain improvements along 100 West, what our options are." (Speaker 2). Engineering staff summarized three options for three intersections on the east side — Center Street, First South and Second South — recommending replacement of existing precast curb inlets with hooded inlets that admit water from the back; the combined price for those three intersections was given as $33,000 (Speaker 1). Center Street was called out as the most expensive of the three because the existing storm pipe is very shallow and would require two cast-in-place boxes rather than a single precast unit (Speaker 1).
For the west side of 100 West, participants discussed several alternatives: installing sumps at First South/First West, adding new pipe to carry overflow to the river, constructing "bubble-up" box culverts that drop under the road then bubble up on the far side, or creating an open waterway. Engineering cautioned that upsizing the underground storm pipe would be a more durable fix but could be many times more expensive because of conflicts with existing utilities (Speaker 1). A bubble-up/box approach was estimated in various combinations to raise the total project cost into the low hundreds of thousands; cumulative estimates during the meeting ranged from roughly $120,000 for a limited set of boxes up to $250,000–$300,000 for a more comprehensive retrofit (multiple speakers).
Nearby residents described local impacts. A participant identified in the discussion as Carlton (Speaker 7) said the flooding at his corner has been severe — he has dug a small ditch himself to redirect flows — and urged targeted measures rather than adding sidewalk where it is not wanted. "I would be of the opinion is to just do a culvert on that road and then just take a blade, dig along this side," Carlton said, describing how water reaches his yard and why a culvert would address that localized problem (Speaker 7).
Participants discussed trade-offs that affect cost and the right-of-way: placing a park strip versus putting the sidewalk next to curb-and-gutter; ADA compliance often requires moving the sidewalk back, which affects driveway transitions. The engineering team noted operational drawbacks to bubble-up boxes, including a tendency for water to remain in the bottom of the box and occasional maintenance when grates are dislodged (Speaker 1).
On funding, staff and council participants reviewed options. The town's typical road budget is about $180,000 annually but portions of those funds are reserved for debt service; B&C road funds currently showed roughly $61,000 on hand (Speaker 4). The current storm drainage fee is $3.75 per month per connection; raising that fee (the meeting mentioned a hypothetical increase to $5.25) could yield on the order of $30,000–$40,000 more per year. Impact fees for new development were discussed but were noted to require a study and a legal basis before adoption (Speaker 4). One suggestion was to ask the nearby church to contribute because some of the church's runoff moves across the town streets; attendees discussed asking the church for $20,000–$25,000 toward the work and Speaker 3 agreed to contact Mitch Carter to open talks.
Faced with limited immediate funds, participants discussed phasing. One practical proposal was to do the east-side inlet replacements and selective curb-and-gutter work first — the meeting noted a partial-scope estimate (east side plus curb and crossway on Farmers' Freeway) in the range of $50,000 — then monitor whether downstream intersections require additional work before committing to the full west-side measures. Speaker 2 summarized the planning target in mid-discussion: "So I think we know what we need to do. It'll be $250,000" and participants discussed ways to phase that cost and explore other funding sources (Speaker 2).
Next steps assigned during the meeting were: verify utility conflicts on the west side (locates and confirm pipe depths), have Speaker 3 contact Mitch Carter at the church to discuss potential cost-sharing, develop a phased scope and a refined cost estimate for inclusion in next year’s road program and bring formal budget options back to the council. The meeting concluded with participants agreeing to pursue those follow-ups and to return with a refined plan and financing options.
The meeting contained no formal motions or votes; the discussion produced a working estimate and a set of follow-ups rather than a final funding decision.