Town hears progress report on pipeline and well work; poles, drilling and pipe pull underway with July target for substantial completion
Summary
Contractor drilling across the marsh and pulling pipe to the field; poles for power are being installed and SRF coordination on drinking-water payments is underway. Well tests returned good results; the project expects substantial work completed by late spring/early summer and final dates around July.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Brennan updated the council on utility work tied to the town’s water and pipeline project. He reported the contractor has drilled across the marsh, reamed pilot holes and prepared to pull pipe into the field; crews are welding pipe sections and beginning to trench toward the 400 block. He said the contractor has also been working to set poles through the marsh and pull power lines, and that crews expect to pull wires into place in the coming weeks.
Brennan said he is coordinating SRF (drinking-water) payment steps and will hold weekly progress meetings on Tuesday afternoons. When asked about completion dates, council members and staff said they were aiming for completion in late spring or summer; one speaker cited a target around July 30 for final substantial completion.
On wells and testing, the council heard that the initial well tests showed good water quality and adequate quantity. The contractor did not encounter significant rock in a bore that had budgeted a rock contingency, generating small savings. Brennan said a remaining coordination step is tying the pump/well installations into Jackson’s trenching work and making final waterline connections to distribution points.
Council members asked about meter-reading issues and on-site valves; staff said they will follow up with the contractor and the district’s contacts. The town did not take new formal action on the pipeline at the meeting, but members requested continued coordination and weekly progress updates.