Residents press for faster Pine Tree Bridge work as council says demolition prep continues
Summary
Residents complained about slow progress after the Pine Tree Bridge was closed for repairs; the town manager said crews have removed guardrails and are working under the bridge on gas- and water-line preparations ahead of demolition and advised residents to document property for potential vibration damage.
Get email alerts on the Pine Tree Bridge topic
No spam. Unsubscribe anytime.
Several residents told the Town of Lake Clarke Shores council on Oct. 8 they are frustrated by perceived slow progress on the Pine Tree Bridge project after the roadway was closed for repairs.
Resident Tim Daughtry said he has seen little visible work and warned the closure is an imposition for people who rely on the corridor. "We've shut the bridge down for 2 weeks and accomplished nothing in 2 weeks' time," Daughtry said during public comment.
Town Manager (Joe) and staff replied that much of the early work is preparatory and occurs under the bridge. Manager Joe said contractors have removed guardrails and are working on the gas line and water-line disconnection to allow safe demolition. He encouraged residents near the work to photograph or videotape property conditions before heavy construction begins as a precaution against vibration-related claims.
Why it matters: The bridge closure affects local circulation and daily commutes, and residents expressed concerns about emergency access and apparent stoppages in field work. Council members asked staff to keep the public updated and explained many early steps — capping utilities and prep work under the structure — will not always be visible from surface observations.
Storm response and safety: The manager and police chief also briefed the council on preparations for an approaching storm; the mayor declared a local state of emergency to enable faster emergency purchases and response. Staff said an after-action report will be prepared if emergency procurement waivers are used.
Next steps: Staff will continue to communicate progress and distribute drone photos on request; council members asked staff to provide clear updates at future meetings and to continue monitoring contractor progress.