Willmar expands North 71 mill-and-overlay after $1.5M state grant; council OKs $305,000 contract amendment and $2.9M preliminary budget

Willmar City Council · November 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Amendment No. 3 to the 2022 engineering contract to broaden project 2503D after the city received a $1.5 million Local Road Improvement grant; amendment is $305,000 and the preliminary project budget is $2,902,700.

The Willmar City Council on Nov. 18 approved a contract amendment and preliminary budget for an expanded North 71 mill-and-overlay project after a state grant changed the project scope.

Public Works Director Justin Leo said initial design work for project 2503D began in 2022, but a recently awarded $1,500,000 Local Road Improvement grant required the city to expand the project south to the Tenth Street/Robins Island entrance. Leo said the enlarged scope requires additional design, grant-administration work and a traffic study to evaluate pedestrian crossing safety on North 71.

Council approved Amendment No. 3 to the 2022 engineering services contract with Bolton & Menk in the amount of $305,000 and adopted a preliminary project budget of $2,902,700; both motions passed by roll call, 8–0. Jared (staff) confirmed the intersection and traffic safety elements will be evaluated as part of the design and provide a later cost estimate for construction decisions.

Leo said the city had originally designed part of the project in 2022 and preferred to keep it under a single contract rather than split it across years. The amendment adds design tasks and grant-administration responsibilities to meet state grant requirements.