Council approves $92,100 in bond refunds for Paul Jensen after warranty holdback
Summary
Preston City Council approved an $89,100 improvement-bond refund and a $3,000 swale-bond refund to property owner Paul Jensen after staff confirmed a 10% warranty holdback. Council debated cleanup of adjacent right-of-way and whether remaining construction items required additional permits.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Preston City Council voted to approve refunds for two bonds tied to work at a Paul Jensen property, approving an $89,100 improvement-bond refund and a $3,000 swale-bond refund on the recommendation of Public Works and the city engineer.
Councilmembers questioned whether residual construction debris and unfinished work in adjacent right-of-way should delay the refunds. City staff explained the project had been treated as a single improvement and that, under city procedure for improvement bonds, the city retains 10% for warranty purposes. As one councilmember put it during the hearing, “Is the 10% enough to cover the warranty?” Staff responded that the 10% holdback is standard for improvement bonds in these circumstances.
John Boles, who the council asked to address on-site conditions, told the council he had spoken with the contractor and described visual observations of unfinished sidewalk work and a cement wall with a gate; he said some vegetation and debris along the right-of-way may predate Jensen’s ownership. Councilmember Todd Thomas moved to approve the refunds “as approved by our public works and engineer,” and an unidentified councilmember seconded the motion; the motion carried following a roll-call vote.
The council directed staff to monitor the area and said they would revisit the swale/right-of-way cleanup if issues remained after 30 days. No additional city funds were allocated; staff said the refunds follow the city’s established bonding and inspection practices.
The council returned to the published agenda after the vote and moved on to a scheduled public hearing on downtown revitalization.