Commission approves multiple procurement and construction actions including contractor-payment authority, liquidated damages and water project award
Summary
The commission approved a package of procurement and infrastructure items: authorization to pay contractors before state SRF reimbursement in some cases, assessment of liquidated damages for RD Phase 1A/1B, awarding a water-system bid to Metro Construction, and multiple task orders and change orders for substation and road projects.
Get email alerts on the Procurement Infrastructure topic
No spam. Unsubscribe anytime.
The Madison City Commission approved several procurement- and construction-related items intended to keep capital projects on schedule and preserve progress where reimbursement timing could cause delays.
Staff presented Resolution 2024-27 to authorize the finance office to make contractor payments in situations where state SRF reimbursement is delayed beyond the city’s 30-day target. Jamieson said the change formalizes prior practice when state reimbursement was taking 10–12 weeks; commissioners asked about accountability controls and staff said approvals would follow cross-checks within the finance office. The commission approved the resolution by voice vote.
On contract performance, staff reported negotiations with a contractor on RD Phase 1A and 1B and recommended assessing liquidated damages of approximately $125,816.66, representing one-third of eligible liquidated damages; staff said verified actual costs from the delays were roughly $101,200. The commission approved the assessment and its proportional allocation across the two projects.
Procurement actions included awarding the Water System Improvement Segment 4 contract to Metro Construction, the low responsible bidder at $776,988.74; and authorizing change order #2 for Lakeview Industrial Park Improvements (Bose Construction) to add pavement replacement on Washington Avenue and a drainage culvert at an increase of $237,643.91 (costs to be shared per existing funding structure). The commission also approved DGR task order amendments for Green Substation (~$6.6M engineer estimate) and Southeast Substation conversion (~$4.0M) to move each project from predesign to final design, and authorized extension work to provide electric service to a Dollar General site and an early learning center.
Commissioners asked for clarity on signatory and cross-check procedures for contractor payments and on cost-share arrangements for change orders. Staff said project reimbursements and grant funding would cover the majority of many expected costs.