Mitchell board commits $30,000 a year for three years to Dakota Riptide to help cover pool debt
Summary
After Dakota Riptide requested $50,000 per year for three years to cover remaining pool-related debt service, the bid board approved a smaller commitment of $30,000 annually for three years (total $90,000), and clarified funds will be applied to debt service obligations through the city.
Get email alerts on the Dakota Riptide Funding topic
No spam. Unsubscribe anytime.
Dakota Riptide, the region’s swim club that pledged private support toward Mitchell’s aquatic center during construction, asked the Bid District 4 board for a three‑year commitment of $50,000 per year to help cover remaining debt service on the pool project. The board voted instead to commit $30,000 per year for three years, a total of $90,000.
Rob Schalski and Jason Weade of Dakota Riptide said the club had pledged $1 million toward the pool originally, had raised roughly $800,000 and reported an outstanding obligation in the mid‑$160,000 range. Schalski and Weade described plans to expand meets (two winter meets, rotation for state meets) and argued consistent support would help the club plan and host events that bring overnight stays and local spending.
Stephanie Alwinette summarized the request: "They're looking for $50,000 a year over the next 3 years that they would use for the debt service payment." Board members debated whether to approve a multi‑year pledge or provide a smaller, year‑by‑year contribution. Some motel owners said they supported continued events but were wary of indefinite obligations; club representatives said a multi‑year pledge would aid fundraising and planning.
After discussion Jason Bradley moved to commit $30,000 per year for the next three years to be applied toward the pool debt service; Tim Smith seconded and the board approved the motion by voice vote. City staff clarified the funds would be applied toward the city's debt service obligation tied to the pool project (not handed directly to the club).
The board asked staff to record the recommendation in its board projects line and to include the commitment in the 2025 budget materials so the City Council can consider final appropriation.