Council approves Schneider Electric pay request; project update says 80% complete and no lead found to date

Mount Pleasant City Council · November 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved pay request No. 6 to Schneider Electric for the water meter replacement project; Schneider's program manager said the project is about 80–82% complete, no lead has been detected in samples reported to TCEQ so far, and a customer portal to monitor usage and detect leaks is being rolled out.

Mount Pleasant's council unanimously approved pay request No. 6 for Schneider Electric as part of the city's water meter replacement project.

Anthony and Schneider Electric staff presented project totals and the pay application; Schneider program manager Craig Messerink said the project has replaced roughly 4,854 meters to date and is about 80% to 82% complete. Messerink also said the project's first lead-and-copper report to the Texas Commission on Environmental Quality (TCEQ) detected no lead in the sampled portion of the installation.

Messerink demonstrated a customer-facing portal and mobile application that allows residents to link accounts to smart meters, see usage trends (hourly, daily, weekly), and receive leak-alert notifications. Staff acknowledged some residents encountered app compatibility issues on older phones; Master Meter is updating its mobile app to address those problems.

During council Q&A, members raised incidents where initial meter readings caused unusually high usage reports; staff said those cases are being addressed individually and urged residents to notify the city for investigation. The council then moved to approve the pay request and recorded a unanimous vote.

The project will continue to completion, and staff said remaining contract balances and final service-line evaluations remain in progress.