Sweetwater accepts standby generator at water treatment plant and releases retainage
Summary
City staff reported the standby generator at the water treatment plant has been installed and operating for months; the council voted to accept the project and release retainage funds to close the job.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
City staff reported the standby generator at the Sweetwater water treatment plant has been installed and has operated reliably for several months, and the council voted to accept the project and release the remaining retainage funds to close out the contract.
An unnamed staff presenter said the generator is running well and that staff requested final acceptance and release of retainage for the project to complete procurement and accounting steps. The council moved, seconded and approved final acceptance by voice vote.
The decision closes the capital project record and authorizes release of retained funds to the contractor. No amendments or further contingencies were described in the meeting record.