Thomas housing project on schedule, town staff says occupancy plans due this fall
Summary
Officials reported the Thomas project buildings are weather-tight, connected to sewer and water, and on track for contractual completion by Jan. 31; an occupancy and management proposal will be presented to council in November or December.
Get email alerts on the Housing Project topic
No spam. Unsubscribe anytime.
Town staff updated the council on progress at the Thomas housing project and described near-term steps for occupancy.
Staff reported the planning board approved a rotation and a small mudroom bump-out; both buildings (referred to as the cape and the ranch) are weather-tight and connected to town sewer and water. Plumbing and electrical contractors have been scheduled and are expected to complete interior systems in the next 45 days; staff said final trim and painting are scheduled between Thanksgiving and Christmas.
The town expects to meet the contractual completion date of Jan. 31 and said it will return to the council in November or December with a proposal detailing how occupancy will be determined, how the program will be run and how rents and management will be set.
Contractor notes: Connecticut Valley Homes is the general contractor for the structures; town staff said the contractor has improved logistics by providing an on-island foreman and using local subcontractors.
What’s next: council to review the occupancy/management proposal and to align final decisions with the consent agreement that governs the project.