Council authorizes $17,500 change order to repair Napoleon Trail connection and add ADA ramp
Summary
Council authorized a change order with Renieri (Rainierie) Construction not to exceed $17,500 to replace damaged asphalt with concrete, build an ADA curb ramp and create a 6‑foot trail connection where soils and contractor access damaged existing pavement.
Get email alerts on the Capital Projects Trail topic
No spam. Unsubscribe anytime.
The Olivette City Council authorized a change order on Sept. 24 to repair a damaged section of the Napoleon Trail connection and make accessibility upgrades.
Mr. McGregor, speaking for city staff, said contractor traffic and unexpectedly poor soils damaged the legacy asphalt connection while crews worked on the Centennial Greenway alignment. Staff proposed replacing the asphalt with concrete, constructing an ADA curb ramp with truncated domes at the cul‑de‑sac, building a 6‑foot trail connection to the existing sidewalk and restoring adjacent topsoil and seed. The net change order amount presented was $17,500.
Councilmember Carl moved to authorize the city manager to sign the change order with Renieri (Rainierie) Construction not to exceed $17,500; the motion passed unanimously on a roll‑call vote.