City management updated the commission on volunteer work in the Rock Inn Black Business District, a pending CDBG grant extension for LFM Park, a delayed Safe Routes to School sidewalk project, Army Corps river-level and survey activity, Vocation Village site-plan progress, rising fire calls, and a planned ARPA allocation workshop after the Dec. 2 meeting.
Get email alerts on the Local Government topic
No spam. Unsubscribe anytime.
The city manager provided a series of operational updates to the commission, covering grants, capital projects and upcoming budgeting steps.
Volunteer and preservation work: The Atchison Historical Society held a volunteer day at the Rock Inn Black Business District, conducting a bake sale and interior demolition; staff reported the building had been stripped to studs and praised strong community participation.
Grants and bidding: The city has requested a grant extension from the Department of Commerce for the LFM Park CDBG grant because initial bids exceeded available funding. Staff plan to rebid components separately to encourage local contractors to participate.
Sidewalk and infrastructure projects: The Safe Routes to School Santa Fe West sidewalk project was reported delayed until late winter or early spring so the contractor can work in better weather; affected residents will be notified. The Army Corps of Engineers gave winter Missouri River level predictions that should allow use of the primary water intake; staff are preparing an auxiliary pump as a contingency. Corps crews have begun surveys for the 15th/16th Street sewer-separation project.
ARPA planning: The commission will hold a workshop after the Dec. 2 meeting to discuss allocation of remaining American Rescue Plan Act (ARPA) funds and intends to pass a resolution at the final meeting of the year to document how remaining ARPA funds will be committed prior to reporting deadlines.
Development and services: Planning Commission-approved site-plan amendments for Vocation Village (Saint Benedict Abbey) on North Second Street would create an early childhood hub offering maternal and family support and childcare services. The fire chief reported unusually high call volume in November, including many lift assists for elderly residents.
Governing comments and next steps: Commissioners thanked staff for visible progress in city projects and cleanliness, recognized long-serving employees, and noted many city staff will work during the Thanksgiving holiday. The commission adjourned to a workshop by voice vote.