Little Falls rejects clarifier rehab bids, plans combined re-bid for 2026
Summary
After bids for a water-treatment clarifier came in above estimates, the council accepted consultant Bolton & Mink’s recommendation to reject the bids and combine the two clarifier projects to seek better pricing for 2026 construction.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City staff reported that three bids for rehabilitation of one clarifier at the Little Falls water treatment facility exceeded budgeted expectations. Greg (city staff) said bidders cited project setup and the need to keep one clarifier operational as factors pushing prices up.
On consultant Bolton & Mink’s recommendation, council voted to reject all three bids and to redesign the work to combine this clarifier with the second clarifier so the city can re-bid both projects together for a 2026 construction timeline. Councilmembers asked whether prices are likely to come down; staff said unit prices may change and the economy of scale from combining projects should reduce overall costs.
The motion to accept the consultant recommendation and reject the bids carried by voice vote; staff will return with updated design and a combined procurement plan.