Rowlett recommends Swinerton as CMAR for $65M municipal complex; preconstruction authorization and GMP schedule presented

Rowlett City Council · September 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff recommended Swinerton Builders as construction manager at risk for the municipal complex, citing competitive pricing and qualifications; staff asked council to authorize preconstruction work and said a guaranteed maximum price will be presented later in the design process.

City staff presented a recommendation to select Swinerton Builders as the construction manager at risk (CMAR) for Rowlett’s municipal complex project, which includes city hall, public safety administration, an animal shelter and Herbert Park.

Christophe Bauer (city management and project staff) explained the two‑step selection process (qualifications then price) and said Swinerton’s overall package was approximately $2.5 million lower than other finalists in the comparative evaluation. Staff requested authorization to begin preconstruction services (a flat preconstruction fee was discussed, and $30,000 was referenced as the typical preconstruction fee), with the guaranteed maximum price (GMP) to be brought back near the end of the construction‑document phase.

The timeline shown to council included a GMP development toward the end of design, a targeted groundbreaking in April 2025 and a ribbon cutting in fall 2026 (staff warned those dates could shift). Council members on the subcommittee and the full council praised the selection process and staff work and asked staff to continue detailed oversight of cost estimating and community engagement.