Board hears capital‑projects update; administration says $1M remains for 2024–25 projects as referendum work continues
Summary
District facilities staff reported year-to-date capital spending, contingency use, and coordination with referendum projects; the board discussed parking-lot timing, masonry deferrals and use of referendum dollars to capture construction efficiencies.
District facilities staff presented an overview of capital improvement projects carried forward from last spring and an update on spending and scheduling.
Ray (Facilities) summarized work that included Huntley asphalt (budgeted $175,000; actual about $191,000 after base and concrete repairs), partial roof replacements (areas 14–19 budgeted $538,000 came in under budget), East Cluster roof repairs ($30,000), and deferred tuckpointing/masonry work at West Cluster…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat