Committee members said closing documents for a new landfill site have been sent and that the sale should finalize in November, allowing site work to begin early next year; bids for a liner project will open Nov. 7 and be presented with recommendations on Nov. 20.
Get email alerts on the Land Acquisition topic
No spam. Unsubscribe anytime.
Committee members received an update on the parish’s pending land purchase for solid waste operations and were told the transaction is close to completion.
Speaker 3 said the cash-sale deed and survey materials have been sent to the seller and described the transaction as much closer than in previous reports. A figure was mentioned orally during the update (the speaker referred to roughly $11,000,220); the committee did not present a signed settlement amount in the meeting record and the price should be verified in closing documents.
Attendees discussed survey work and flagged that physical survey stakes or corner posts have not yet been placed. Staff were asked to coordinate marking corners and to ensure access roads are cleared inside the property line to meet permit requirements. One participant said the parish must build access roads around the entire perimeter as required by permits.
Speakers said the land transaction is expected to be finalized in November and that initial site work could begin at the start of the year; a preliminary site-development timeline discussed in the meeting ranged up to about 12–18 months for initial phases. Speaker 6 reported that bids for a liner/lifting project will open on Nov. 7; staff will review bids and bring a recommendation with quotes to the committee on Nov. 20.
The meeting also covered equipment needs tied to the site: Speaker 5 said an 8-inch pump is in the project scope and that the parish has been renting pumps while awaiting repairs on earlier purchases. Speakers noted the gas-collection partner will not have compression online for about 18 months, an item participants said they must account for while conserving collected gas.
The committee did not execute final purchase documents during the session; members asked staff to finish closing steps, place permanent survey markers, and return with formal recommendations and procurement quotes for construction and liner work.