Pickens County earmarks major Henderson Mountain waterline and paving work for 2025; multi-contract bids expected

Pickens County Board of Commissioners (work session) · December 2, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County leaders flagged a significant 2025 project for Henderson Mountain that will require replacing a failing waterline before paving — a two-contractor sequencing that could cost an estimated $2.4–$2.8 million and requires close coordination on bids and traffic control.

Speaker 1 told board members the county's most significant 2025 paving priority is Henderson Mountain, where repeated waterline ruptures and difficult terrain require first replacing the water main and then repaving the road. "It's a combination of replacing the waterline and repaving the road," Speaker 1 said, adding that vibration from the current PVC line has caused repeated failures.

He described the work as two linked procurements: separate bids for the waterline and paving contractors that must be coordinated to avoid long periods when the road would remain torn up between operations. Traffic control will be complicated because of steep drops and narrow right-of-way in several stretches. Speaker 1 said initial contractor conversations suggested the waterline work could take months depending on rock conditions and that the county aims to begin waterline work in spring and paving in summer to limit impacts to school bus traffic.

Speaker 1 estimated the combined waterline and paving work could fall in a $2.4–$2.8 million range and said bid packages will be prepared so the county can move quickly next year. He said the county will evaluate durable pipe options to avoid recurring failures and that the project has been deferred for many years.