EDC staff reported multiple business inquiries seeking acreage and rail access, progress on a Regional Foreign Trade Zone study, and ongoing expansion talks with Lincoln Lumber and other firms; a Crockett Construction donation was noted for gateway signage.
Get email alerts on the Edc Pipeline topic
No spam. Unsubscribe anytime.
EDC staff used the Oct. 21 joint meeting to present a broad development update, saying the council’s development group had received multiple inquiries and that a Regional Foreign Trade Zone (FTZ) study is nearing a draft stage.
Speaker 11 (EDC staff) listed three active inquiries: an equipment sales and remediation company seeking 10 acres with rail access, an agriculture producer seeking 3–4 acres to support approximately 40 jobs, and a forest‑products business exploring on‑site electricity generation. Staff said a consultant, James Grogan, told the EDC that the FTZ study is complete and that a draft letter to support an FTZ application should be available within the week; staff expressed optimism that the EDC could assemble an application by year‑end.
The presentation also highlighted existing projects and expansions: Lincoln Lumber is considering an expansion that staff estimated could add 8–10 jobs and involve additional investment (numbers in the transcript are approximate), and other projects in play include Genex/A&A and Provallis, which the presenter said together could add roughly 50 jobs. Staff said retail inquiries and negotiations with firms such as Harbor Freight and Goodwill are underway for an Eastgate shopping center site, and that permitting is under review for a Take 5 Oil Change. The EDC representative reiterated that some projects will require negotiation of abatements and other incentives if expansions move forward.
On gateway signage, staff reported a donation from Crockett Construction toward a sign (donation listed in the packet as $20,477) and said EDC approval to purchase one sign would reduce the remaining project need to roughly $81,000. The council approved EDC purchasing one sign.
Speakers framed the FTZ work and business inquiries as opportunities to diversify the local economy, and they asked the council to continue coordinating permitting, abatements and outreach to recruitment partners.